As you may have noticed, Phase I work has started this week on the Municipal Parking Lot at Town Hall. This week is concrete work and some minor reconfiguration. There may be some very temporary traffic pattern changes during this work. The Lot will remain open. We anticipate 3-5 days for this phase to complete.
After this work, Phase 2 is scheduled to begin on 10/15/2024. This work is anticipated to take 4-5 days. There will be some parking closures during this phase. More communication will go out as we get closer to the October 15th Phase 2 start date.
The last Phase will be painting the parking lot lines on the new surface. This will take place immediately after the new surface is cool enough. This should take 1 day. The Lot will be open during this process.
These large projects always come with a few unplanned issues. We ask for your patience during this very needed work.
Look to this page for additional updates.